Resembling a large screw, screw piles are installed deep into the ground, beneath the ground freezing level, to solidly support the structure of the Clubhouse. This is an advantageous alternative to form tubes and is less expensive than concrete foundations. For MTC, 15 screws were installed with a torque of 5000 psi at and average depth of 11 feet.

 

Listen to Chris as he describes the screw pile system:

 

Watch the complete process of installing the screw piles and installing the completed floor joists:

 

 

 


 

 

 

 

 

To read more about this foundation system, visit: http://www.goliathtechpiles.com/our-piles/ 

 